Chemical Spill 10 (CS-10) Groundwater
Plume
Source of the Plume
The primary sources of the CS-10 groundwater plume are the 38-acre area of the former
Boeing Michigan Aeronautical Research Center (BOMARC) Missile Site and Unit Training
Equipment Site (UTES) located near the eastern boundary of the MMR. The BOMARC Missile
Site was operated between 1962 and 1973, and UTES has operated since 1978 to maintain and
store armored and other wheeled vehicles. Spills and releases of chemicals occurred in
these areas in the past. A preliminary pollution prevention program has been in place at
UTES since December 1995 to ensure that petroleum use and disposal do not affect the
groundwater.
For the BOMARC site, the remedial investigation, which defines the nature and extent of
contamination, has been completed. A feasibility study, which outlines alternatives for
treating the contamination, also has been completed. A proposed plan, which describes
AFCEEs preferred alternative for addressing the site, will be released for public
comment in early fall 1998. Following public comment, a record of decision describing the
final decision will be released; it is scheduled for late 1998. Once the record of
decision has been signed, design and construction of the selected remedy will begin.

Primary Contaminants
The primary contaminants of the CS-10 plume are TCE, PCE, and 1,2 dichloroethylene
(1,2-DCE). TCE has been detected in the western portion of the plume as high as 400 ppb,
and in the southeastern portion of the plume as high as 2,800 ppb, although there have
been isolated detections of higher concentrations. EDB has been detected sporadically at
low levels. The safe drinking water standard, or maximum contaminant level, is 5 ppb for
TCE, PCE, and 1,2-DCE. PCE and TCE are common solvents used for equipment maintenance and
degreasing. EDB was added to leaded gasoline, including aviation gasoline (AVGAS), to
inhibit the build-up of lead in engines.
Affected Area
Most of the CS-10 plume affects the south-central area of the base. The plume is about
17,000 feet long, a maximum of 4,000 feet wide, and up to 140 feet thick. In general, the
plume is more than 120 feet below ground and 60 feet below the water table along most of
its length.
The eastern lobe of the plume has migrated off-base in the groundwater near the
Falmouth Gate. It has been tracked to the edge of Ashumet Pond. Additional drilling and
sampling is scheduled to begin in October 1998 to determine whether the plume is flowing
deep under Ashumet Pond. None of the primary contaminants in the plume have been detected
in the surface water of Ashumet Pond.
Plume Cleanup
Two pilot tests of recirculating wells began in the eastern lobe of the CS-10 plume
near the boundary of the base in December 1996 and are scheduled to run until 1999.
The CS-10 plume was one of four plumes to go through the "decision criteria"
process in 1997, a public process that enabled the remedial project managers and the
public to compare and evaluate cleanup alternatives.
In August 1997, after careful consideration of the advantages and disadvantages of each
plume response alternative and comments received during the public comment period, the
remedial project managers from AFCEE, EPA, and MassDEP decided on an alternative to treat
the CS-10 plume. The selected alternative uses ETR technology. An extraction fence
will be constructed along Sandwich Road; it is expected to be activated in May 1999, at
which time the recirculation well pilot systems will be shut off. Active remedial systems
will be evaluated for their effectiveness within the body of the plume. An ETR fence is
under consideration along the southern portion of the plume; however, results of the
Southwest Operable Unit (SWOU) study must be considered before design of the system
begins.
Next Steps
- Monitoring wells were installed during the spring, 1998. Ongoing ecological sampling is
being conducted. A total of 34 wells were sampled for data gap analysis to prepare the
engineering design.
- Engineering design of the selected alternative is underway and will continue throughout
1998. The plans will be available to the public.
- Information updates will be provided to the public periodically.
- AFCEE representatives will meet with neighborhood and other community groups at any
time, as requested.
- Extensive coordination among AFCEE, EPA, DEP, and citizen advisory teams will continue.
- AFCEE, EPA, and MassDEP encourage residents to attend citizen advisory team and public
meetings, become more informed and involved with the cleanup, and sign up for the site
mailing list to receive updates.
- The public will be notified before phased construction of system elements begins.
- System startup will be phased with construction to meet enforceable milestones.
- The enforceable milestone for full-scale system startup is May 31, 1999, for the
Sandwich Road fence, and June 28, 1999 for the selected in-plume system.

Boeing Michigan Aeronautical Research Center(BOMARC) Missile Site
and Unit Training Equipment Site (UTES)

Reseeding the Road Shoulder at FS-12 |