March 1, 2001
NEIGHBORHOOD NOTICE
Dear Resident,
The Air Force Center for Environmental Excellence (AFCEE) is committed
to protecting public health. As part of this commitment, we wish to provide you with an
update on the cleanup system operations in your neighborhood.
Storm Drain 5 South Recirculating Wells Update
Since June 1999, two recirculating well treatment systems, located
below Hillside Avenue and Wheeler Road, have been cleaning contaminated groundwater from
the Storm Drain 5 South (SD-5S) groundwater plume. Through the end of December 2000, both
recirculating wells have treated a total of 84 million gallons of groundwater. In response
to neighborhood concerns, modifications were made in 1999 to both systems. These
modifications eliminated the discharge of air from the systems to the ambient air outside
of each vault. Subsequent monthly air and water samples collected from each system
indicated they were operating efficiently with the modifications. Therefore, vent pipes
and associated support poles were removed in August 2000.
The greatest concentration of trichloroethylene (TCE) detected in
groundwater being treated at the Hillside Avenue treatment system was 22.0 parts per
billion (ppb) when it first started operating in June 1999. Measured TCE concentrations
have decreased over time, but currently are detectable in water samples collected from the
system above the TCE Maximum Contaminant Level (MCL) of 5 ppb. The MCL is the maximum
concentration of a given contaminant allowed in drinking water under the federal Safe
Drinking Water Act. The Hillside Avenue system currently treats 60 gallons of contaminated
groundwater per minute.
The greatest concentration of TCE detected in groundwater being treated at
the Wheeler Road recirculating well treatment system was 14.1 ppb when it first started
operating in June 1999. TCE concentrations detected in samples collected from the system
have decreased over time and since August 2000 have not been detectable when analyzed.
Since July 1999, no detections of TCE above its MCL (5 ppb) have been measured in samples
collected from groundwater monitoring wells located upgradient (the area from which
groundwater flows) of the Wheeler Road system. In addition, no contaminants have been
detected in samples collected from groundwater monitoring wells located immediately
downgradient (the area toward which groundwater flows) of the Wheeler Road system since
December 1999.
Based on the information above, AFCEE recommended to the U.S.
Environmental Protection Agency (EPA) and the Massachusetts Department of Environmental
Protection (DEP) in mid-December 2000 that the Wheeler Road recirculating well treatment
system be shut down temporarily. At that time, AFCEE also recommended sampling additional
groundwater monitoring wells near the Wheeler Road area. On December 28, 2000, the Wheeler
Road treatment system stopped operating because of a mechanical failure. AFCEE decided not
to repair the well due to its recommendation to shut down the well temporarily. EPA and
MassDEP reviewed AFCEEs proposal and agreed to keep the well temporarily shut down.
The operation of the Wheeler Road recirculating well will be discussed
at the March 7, 2001, Joint Process Action Team (JPAT) meeting to be held at the Falmouth
Holiday Inn, starting at 5:30 p.m., with this discussion scheduled on the agenda for 7:30
p.m.
Chemical Spill 10 and Storm Drain 5 South Treatment System Update
Two extraction wells, located on Hooppole Road, are associated with
cleaning up portions of the Chemical Spill 10 (CS-10) groundwater plume and the remaining
portions of the SD-5S groundwater plume not being cleaned up by the recirculating well
treatment systems. Together, the two extraction wells continue to pump 175 gallons per
minute of contaminated groundwater through double-walled pipes to the Sandwich Road
Treatment Plant. The clean water is returned to the aquifer using re-injection wells
located near the plant.
As of January 1, 2001, a total of approximately 81.5 million gallons of
groundwater have been pumped since the wells began operating on January 22, 2000. Workers
will continue requiring access to extraction well vaults on a periodic basis to perform
routine operation and maintenance work. Based on direction from the Mashpee Department of
Public Works, Hooppole Road will be re-paved this year.
Chemical Spill-10 Investigation Update
During the 2000 summer season, six additional groundwater monitoring wells
were installed along Hooppole Road. This work was performed as part of the
continuing CS-10 investigative work. The data collected from these monitoring wells helped
engineers determine the location for two additional monitoring wells installed east of
Johns Pond in October and November 2000. These eight additional wells helped identify the
leading edge of the CS-10 groundwater plume. The results of that CS-10 investigative work
will be presented at informational meetings to be held this spring and summer. Meetings
will be held in an informal poster board setting, allowing for direct interaction with
AFCEE project managers, and program engineers and scientists.
Ashumet and Johns Ponds
Informational Meetings
Wednesday, May 30, 2001 And Tuesday, August 14, 2001
Mashpee Town Hall, Room 2
from: 6 pm-8 pm
For more information about these projects or meetings, please call
Lana Brodziak, AFCEE Community Involvement Specialist, at (508) 968-4670 extension 5981.