NEWS RELEASE
2005-20 MASSACHUSETTS MILITARY RESERVATION, Cape Cod, Mass.
As part of the Air Force Center for Environmental Excellences (AFCEE) Southwest
Plumes Treatment Construction Project, AFCEE would like to announce upcoming traffic
changes for Hatchville residents and users of Boxberry Hill Road. From August 15, 2005 through August 26, 2005, Boxberry Hill Road (between
Route 151 and Hatchville Road) will have sections of the road completely closed. The
map on page 2 shows the location of this construction project as well as the closed
sections and dates of construction. · Work hours will be
extended to M-F, 7:30 AM - 7:00 P.M, so that Boxberry Hill Road will remain open on the
weekends with 2-lane traffic at all work area locations. Trenching
operations:
Work location
at the corner of Brady Drive and Boxberry Hill Road: o From August 15 through August
19 one lane open during construction o From August 22 through August
26 - Boxberry Hill Road closed at this location. o From September 9 through
September 19 one lane open during construction. Work location
in between #495 Boxberry Hill and #550 Boxberry Hill Road o From August 8 through August
12 one lane open during construction o From August 15 through August
19 - Boxberry Hill Road closed at this location. o From August 22 through
September 2 one lane open during construction. For more information, please call Mr. Doug Karson, AFCEE Community Involvement
Lead at 508-968-4670 ext. 4678. You can also get updated construction information at
our website: http://www.mmr.org/construction/groundconstproj.htm
|