| Fact Sheet #2000-08 October 2000 Federal Facility Agreement (FFA) Schedule Amendments A fact sheet providing an update on the Federal Facility Agreement Schedules The purpose of this fact sheet is to describe the updates that have been made to the schedules, which are part of the revised Federal Facility Agreement (FFA) signed in 2000.
Words that appear in italics are defined in the glossary at the end of this fact sheet. This fact sheet is an update to a previously published one (#99-10 in October 1999). The following acronyms are used throughout this document: (CS) Chemical Spill; (CY) Coal Yard; (FS) Fuel Spill; (FTA) Fire Training Area; (LF) Landfill and (SD) Storm Drain. Background The first schedule, contained in Appendix III, Timetable 2 of the FFA, established enforceable deadlines for ongoing source control actions at the MMR. Specifically, this schedule sets deadlines for decisions for areas requiring soil and/or sediment cleanup. The second schedule contains the enforceable deadlines pertaining to groundwater plume response actions, the cleanup of contaminated groundwater, at and originating from the MMR. This schedule was added to the FFA as Appendix III, Timetable 3 on May 30, 1997. The attached FFA Milestone Changes Summary table indicates where changes to previous deadlines have been made. The table references a source area or groundwater plume, the document to which the deadline applies, the former date, the revised date, and the justification for making the change. EPA has agreed to the noted changes. EPA and the Air Force Center for Environmental Excellence (AFCEE) have consulted with the Commonwealth of Massachusetts Department of Environmental Protection (DEP) regarding these changes. Source Area Actions CS-16/CS-17, CS-10/FS-24, SD-5/FS-5, SD-3/FTA-3/CY-4, SD-4, SD-2/FS-6/FS-8, CS-5, CS-11, Drum Disposal Unit (DDOU), FS-18, CS-4(CG)/FS-1 (CG), FS-7, and FS-9: The Record of Decision (ROD) for these sites specified asphalt batching as the agreed option for cleanup. After the ROD was signed, new milestones for these sites were added to the FFA, as required.
CS-10/FS-24(Detail C), Petroleum Fuel Storage Area (PFSA)/FS-10/FS-11 and FTA-2/LF-2: The Record of Decision (ROD) for these sites specified soil vapor extraction (SVE) and biosparging as the agreed option for cleanup. After the ROD was signed, new milestones for these sites were added to the FFA, as required.
Fuel Spill 2 (FS-2): Originally, the FS-2 site was to be considered part of the Southwest Operable Unit (SWOU) program. After review by the regulatory agencies, the FS-2 site was then listed individually, and thus new FFA milestones were added.
Groundwater Plume Response Actions Ashumet Valley (Axial): Pursuant to provisions of Section VII and XIV of the FFA between AFCEE, the NGB, and EPA, new milestones were added to the FFA in 2000.
Chemical Spill 10 (CS-10) Groundwater Operable Unit: In 1999, new enforceable deadlines were added to the FFA to finalize previous cleanup decisions for the entire CS-10 groundwater operable unit. However, AFCEE and the regulatory agencies have decided that additional investigative work must be accomplished in the area of Ashumet and Johns Ponds that was not part of the original (RI) scope of work. This additional work has necessitated a change in the enforceable milestone.
Chemical Spill 10 (Sandwich Road, In-plume, and Southern/Southwest): Pursuant to provisions of Section VII and XIV of the FFA between AFCEE, the NGB, and EPA, new milestones for the submission of the Draft Interim Remedial Action Closeout Report were added to the FFA in 2000.
Chemical Spill 19 (CS-19): The newly revised milestone dates reflect those changes based on the non-availability of funding, which was determined by the regulatory agencies to be in accordance with the "Force Majeure" provision under the FFA. Furthermore, the current agreement to perform additional investigations at the CS-19 site in 2000-2001 have also required a change or extension to some of the original schedules.
Fuel Spill 1 (FS-1): After the FS-1 ROD was signed, new milestones for this groundwater plume were added, as required by the FFA.
Fuel Spill 12 (FS-12): Pursuant to provisions of Section VII and XIV of the FFA between AFCEE, the NGB, and EPA, new milestones for the submission of the Draft Interim Remedial Action Closeout Report were added to the FFA in 2000.
Landfill 1 (LF-1): Pursuant to provisions of Section VII and XIV of the FFA between AFCEE, the NGB, and EPA, new milestones for the submission of the Draft Interim Remedial Action Closeout Report were added to the FFA in 2000.
Storm Drain 5 (SD-5 North and South): Pursuant to provisions of Section VII and XIV of the FFA between AFCEE, the NGB, and EPA, new milestones for the submission of the Draft Interim Remedial Action Closeout Report were added to the FFA in 2000.
Southwest Operable Unit (SWOU-Phase II): A 45-day extension was added to the normal 30-day public comment period on the Proposed Plan for the FS-28/29 groundwater plumes at the request of the public. This activity impacted the previously agreed to schedule.
GLOSSARY biosparging—Biosparging is the use of injected air (oxygen) into soil or groundwater to speed up bioremediation-a treatment process where naturally occurring microorganisms (yeast, fungi, or bacteria) breaks down hazardous substances into less toxic or nontoxic substances. cold-mix asphalt batching—Cold-mix asphalt batching is a process where soils with low concentrations of contaminants are made into paving material by the addition of a heated emulsion at less than 120°F. The process is regulated by the Massachusetts Department of Environmental Protection (DEP) and the final product is used statewide as a base under asphalt paved surfaces. enforceable deadlines—the time limitation applicable to issuance by the lead agency of all primary documents up to an including all record of decisions (RODs) for which a limitation has been specifically established under the terms of the FFA. Also sometimes referred to as enforceable milestones. Feasibility Study (FS)—a report that identifies and screens potential cleanup alternatives for a site that requires further remedial action. Force Majeure—any event arising from causes beyond the control of the party that causes a delay in, or prevents the, performance of any obligation. Proposed Plan (PP)—a document that summarizes the preferred remedial action for a site and presents the rationale for the preference. Record of Decision (ROD)—a document presenting the remedial action selected under agreement with the regulatory agencies and also includes a record of public comments and the responsiveness summary Remedial Action Closeout Report—The Remedial Action Report documents the activities that occur under each specific remedial action operable unit at a site. It also provides documentation that a particular operable unit has met its objectives, and certifies that all items in the settlement agreement and any incorporated documents have been met. Remedial Investigation (RI)—an investigation to gather and analyze data necessary to determine the nature and extent of contamination of a site. Soil Vapor Extraction (SVE)— SVE extracts contaminants from the soil in vapor form. By applying an air vacuum through a system of underground wells, contaminants are pulled to the surface in vapor form. Often, in addition to vacuum extraction wells, air injection wells are installed to increase the airflow and improve the removal rate of the contaminant vapor. Vapors extracted by the SVE process are typically treated using carbon filtration. Once the carbon filters are spent, they are taken off-site and recycled. Source Area Workplan Addendum—a site specific workplan that delineates the boundaries of impacted soils for excavation and/or on-site remediation. Wellfield Design Report—a document that denotes the complete design for remediation of a specific site, most often involving groundwater plumes. The report details the approximate number, location, and type of extraction wells needed and also what type of discharge from the treatment plant there will be (i.e. reinjection, infiltration gallery or surface). For more information: Doug Karson, Community Involvement Specialist Jim Murphy, Community Involvement Coordinator
Table 1: FFA Milestone Changes Summary SOURCE AREA RESPONSE ACTIONS
Deadlines were based on a comparison between:
Table 1 (con’t): FFA Milestone Changes Summary GROUNDWATER PLUME RESPONSE ACTIONS
Deadlines were based on a comparison between:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||