Fact Sheet #99-10 Federal Facility Agreement (FFA) Schedule Amendments A fact sheet providing an update on the Federal Facility Agreement Schedules The purpose of this fact sheet is to describe the updates that have been made to the schedules, which are part of the Federal Facility Agreement (FFA).
Words that appear in italics are defined in the glossary at the end of this fact sheet. This fact sheet is an update to a previously published one (#98-15 in September 1998). Background The first schedule, contained in Appendix III, Timetable 2 of the FFA, established enforceable deadlines for ongoing source control actions at the MMR. Specifically, this schedule sets deadlines for decisions for areas requiring soil and sediment cleanup. The second schedule contains the enforceable deadlines pertaining to plume response actions, the cleanup of contaminated groundwater, at and originating from the MMR. This schedule was added to the FFA as Appendix III, Timetable 3 on May 30, 1997. The attached FFA Milestone Changes Summary Table indicates where changes to previous deadlines have been made. The table references the source area or the plume affected, the document to which the deadline applies, the former date, the revised date, and the justification for making the change. EPA has agreed to the changes. EPA and the Air Force Center for Environmental Excellence (AFCEE) have consulted with the Commonwealth of Massachusetts Department of Environmental Protection (DEP) regarding these changes. Source Area Actions The study areas, U.S. Coast Guard Chemical Spill 8 (USCG CS-8) and Chemical Spill 22 (CS-22) have been added to the FFA. These study areas are currently undergoing a preliminary assessment/site investigation (PA/SI) and enforceable deadlines will be established if and when a remedial investigation & feasibility study (RI/FS) is warranted. Priority 2 & 3 Sites/Drum Disposal Operable Unit (DDOU): In accordance with the requirements of the FFA, enforceable deadlines for these sites were added to the FFA upon completion of the Action Memorandum. More specifically, the submittal of the draft 100% remedial design as a result of the Engineering Evaluation/Cost Analysis (EE/CA) and Action Memorandum that was signed in June 1999 was added. The Priority 2 & 3 sites are made up of the following: Chemical Spill 5 (CS-5), Chemical Spill 11 (CS-11), Chemical Spill 15 (CS-15), Fuel Spill 4 (FS-4), Fuel Spill 18 (FS-18), United States Coast Guard Chemical Spill 4 (USCG CS-4), United States Coast Guard Fuel Spill 1 (USCG FS-1), the DDOU and Fuel Spill 7 (FS-7).
Fuel Spill 1 (FS-1): For the FS-1 source area, additional alternatives analysis and resubmittal of the feasibility study (FS) were required prior to proceeding with the Proposed Plan (PP) and ROD process.
Groundwater Plume Response Actions Ashumet Valley (Pond Fence): In lieu of an active remedial system startup of the Ashumet Valley pond fence, the FFA milestone was modified to recognize the submittal of the draft Phosphorus Management Plan.
Chemical Spill 10 (CS-10) Groundwater Operable Unit: New enforceable deadlines were added to the FFA to finalize previous decisions leading to the ROD for the entire CS-10 groundwater operable unit. New sets of enforceable FFA deadlines were agreed upon, as listed below. There were no old FFA dates associated with these new additions to the FFA.
Chemical Spill 10 (CS-10) South/Southwest Fence: A new FFA date was added to meet the previously agreed upon full system startup date of April 30, 2000.
Storm Drain 5 South (SD-5S): In accordance with the original FFA deadline (June 22, 1999), two re-circulating wells were installed in the main body of the SD-5S plume. Several changes have been made in the remedial approach to cleaning up the remainder of the SD-5S plume. Recent investigations in that area discovered a new plume area (TCE plume) between Ashumet and Johns Ponds. Consequently, a Time Critical Removal Action (TCRA) was added for the TCE plume and to further capture the leading edge of the SD-5S plume.
Southwest Operable Unit (SWOU, phase I): During the SWOU investigation, several new plume areas were discovered- CS-20 and CS-21. CS-4 and FS-13 were already known before the SWOU investigation. Due to the complex nature of CS-4, CS-20, CS-21 and FS-13, the public comment period on the proposed plan was extended from 30 days to 60 days.
Southwest Operable Unit (SWOU-Phase II): As part of the original SWOU program to investigate the already known FS-28 plume area, another plume area, FS-29 was discovered. Based on regulatory input, the FS-28 and FS-29 plumes were separated into a second phase of the SWOU program. Additional data collection was required by the regulatory agencies and additional remedial alternatives were requested for those plumes based upon this additional work. This was a modification of the original scope of work in the SWOU program. New sets of enforceable FFA deadlines were agreed upon, as listed below.
Fuel Spill 1 (FS-1): For the FS-1 groundwater plume, additional alternatives analysis and resubmittal of the feasibility study (FS) were required prior to proceeding with the Proposed Plan (PP) and ROD process.
GLOSSARY Action MemorandumA decision document that presents the selected removal action alternative and explains the rationale for the selection. The Action Memorandum also includes responses to public comments and concerns raised during the comment period. enforceable deadlinesthe time limitations applicable to issuance by the lead agency of all primary documents up to an including all record of decisions (RODs) for which a limitation has been specifically established under the terms of the FFA. Engineering Evaluation/Cost Analysis (EE/CA)An expedited Superfund process of identifying and evaluating cleanup alternatives for a site where there is a potential threat to human health or the environment. The EE/CA must be made available for a 30-day public comment period prior to the signing of the Action Memorandum. extraction, treatment, and reinjection (ETR)a system that extracts groundwater, treats it to reduce or eliminate contaminants and reinjects the treated water into the aquifer. Feasibility Study (FS)a report that identifies and screens potential cleanup alternatives for a site that requires further remedial action. Phosphorus Management Plana document that evaluates pond phosphorus management options. It offers various remedial approaches to phosphorus loading to surface water bodies, namely Ashumet Pond. Preliminary Assessment/Site Investigation (PA/SI)- The Preliminary Assessment (PA) and Site Inspection (SI) are used by EPA to evaluate the potential for a release of hazardous substances from a site. Proposed Plan (PP)a document that summarizes the preferred remedial action for a site and presents the rationale for the preference. Record of Decision (ROD)a document presenting the remedial action selected under agreement with the regulatory agencies and also includes a record of public comments and the responsiveness summary Remedial Investigation/Feasibility Study (RI/FS)an investigation to gather and analyze data necessary to determine the nature and extent of contamination of a site. A feasibility study identifies and screens potential cleanup alternatives for a site that requires further remedial action. Time Critical Removal Action (TCRA)a regulatory approach used when quick actions are needed to clean up a hazardous material spill, but when fewer than six months are available to design the treatment system. 100% Remedial Designplans, drawings and specifications for a remedial action alternative suited for a specific site. For more information: Doug Karson, Community Involvement Specialist Jim Murphy, Community Involvement Coordinator Table 1: FFA Milestone Changes Summary
Deadlines were based on a comparison between: Table 1 (contd): FFA Milestone
Changes Summary
Deadlines were based on a comparison between: Click here to download Appendix
III, timetable 2 in excel format |
| Site | Draft Site Investigation (12) | Draft Decision Document | Final Decision Document (12) | Draft RI/FS Work Plan | Draft Remedial Investigation | Draft Feasibility Study | Draft Proposed Plan | Draft Record of Decision | FINAL Record of Decision (12) | Draft 100% Remedial Design | Draft Project Closeout Report |
| CY-2 Former USAF/ANG Coal Yard Storage Yard | Aug-88 | Mar-88 | F Oct 88 | ||||||||
| CS-10 Tank Wash Operable Unit | Mar-89 | Oct-89 | F Feb 90 | ||||||||
| FS-20 Current Product Tank 88 | Mar-89 | Jan-90 | F Feb 90 | ||||||||
| LF-5 VA Cemetery Rubble Landfill (1) | F Aug 90 | ||||||||||
| LF-6 USN Rubble Landfill (1) | F Aug 90 | ||||||||||
| LF-7 Radon Tube Burial Landfill (1) | F Aug 90 | ||||||||||
| CS-7 Organizational Maintenance Shop 6 (1) | F Aug 90 | ||||||||||
| CS-12 VA Cemetery Roads and Grounds Shop (1) | F Aug 90 | ||||||||||
| FS-15 Runway #5 Fuel Spill (1) | F Aug 90 | ||||||||||
| FS-16 Helicopter Maintenance (1) | F Aug 90 | ||||||||||
| CS-5 CG Carpentry Shop (1) | F Aug 90 | ||||||||||
| CS-7 CG Dry Cleaning Facility (1) | F Aug 90 | ||||||||||
| LF-2 CG Rubble Landfill (1) | F Aug 90 | ||||||||||
| LF-3 CG Rubble Landfill (1) | F Aug 90 | ||||||||||
| LF-1 CG Rubble Landfill | Nov-93 | Oct-94 | F Dec 95 | ||||||||
| LF-3 Northeast Landfill | Aug-96 | F Apr 97 | |||||||||
| FS-25 Building 167 Area Fuel Spill | Jul-88 | Oct-92 | F Jun 97 | ||||||||
| FS-26 Building 3444 Fuel Tank Area USCG | Jul-93 | Sep-94 | F Jul 97 | ||||||||
| CY-1 Former Army/VA Hospital Coal Yard | Mar-92 | ||||||||||
| CY-3 Former Army/VA Hospital Coal Yard | Mar-92 | ||||||||||
| FS-3 Johns Pond Road Fuel Dump | Jun-90 | Oct-93 | |||||||||
| CS-6 Current ANG Maintenance Shop | Jul-93 | Dec-94 | |||||||||
| FS-22 ANG Motor Pool | Jul-93 | Dec-94 | |||||||||
| CS-6 Other Maintenance Shops USCG | Nov-93 | Feb-95 | |||||||||
| FS-2 CG Hot-Mix Asphalt Plant | Nov-93 | Mar-97 | |||||||||
| CS-1 North Truck Road Motor Pool | Jul-93 | Apr-97 | |||||||||
| CS-2 East Truck Road Motor Pool | Jul-93 | Apr-97 | |||||||||
| CS-3 South Truck Road Motor Pool | Jun-90 | May-97 | |||||||||
| CS-8 Organizational Maintenance Shop 22 | Jun-90 | May-97 | |||||||||
| CS-8 CG/ CS-22 (13) | |||||||||||
| FS-21 Current Product Tank 90 | Jun-90 | May-97 | |||||||||
| FS-23 South Truck Road Fuel Spill | Jun-90 | May-97 | |||||||||
| CS-9 Former Main USAF Motor Pool | Nov-93 | May-97 | F Jun 98 | ||||||||
| CS-14 Building 156 Leach Pit | Nov-93 | May-97 | |||||||||
| FS-14 Range E-3 Spill | Jul-95 | May-97 | |||||||||
| CS-2 CG Hanger 3170 Areas | Nov-93 | Jun-97 | |||||||||
| SD-1 Storm Drainage Disposal Site | Jun-90 | Sep-97 | |||||||||
| FS-27 Connery Ave Telephone Line Soil Excavation | Jul-93 | Dec-97 | |||||||||
| FS-2 Railroad Fuel Station (2) | Feb-90 | 29-Oct-98 | TBD | TBD | TBD | ||||||
| CS-4 West Truck Road Motor Pool (3) | Sep-94 | ||||||||||
| CS-4 (North) West Truck Road Motor Pool (4) | Jun-97 | ||||||||||
| CS-18 Propellant Burning Area (5) | Jun-95 | ||||||||||
| CS-19 Impact Range Chemical Dump Site (5) | Jun-95 | 14-Aug-99 | 27-Apr-00 | 23-Sep-00 | 19-Jan-01 | 23-Jun-01 | 29-Oct-01 | ||||
| LF-1 MMR Main Sanitary Landfill Source | Feb-90 | Jun-90 | Mar-92 | Jun-92 | Jun-92 | Aug-92 | F Jan 93 | Jul-94 | Jul-96 | ||
| LF-1 Source Northwest Groundwater Operable Unit (6) | |||||||||||
| FS-12 Underground Fuel Line Range (7) | Oct-90 | ||||||||||
| FTA-1 Current Fire Training Area Source (8) | Jul-88 | ||||||||||
| CS-1 CG Transmitter Site | Mar-89 | Sep-92 | Aug-93 | Jul-94 | Mar-95 | F Sept 95 | |||||
| 6 Area of Concern Source Area Cleanup | |||||||||||
| SD-2 Storm Drainage Disposal Site (9) | Feb-90 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| SD-3 Storm Drainage Disposal Site (9) | Mar-89 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| SD-4 Storm Drainage Disposal Site (9) | Nov-93 | May-93 | Sep-94 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| SD-5 Storm Drainage Disposal Site - Source (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| LF-2 Original Base Landfill (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FS-5 Apron Near Aquafarm (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FS-6 Airfield Apron (9) | Feb-90 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FS-8 Airfield Apron (9) | Feb-90 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FS-10 Petroleum Fuel Storage Area (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FS-11 Fuel Storage Area (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| Petroleum Fuels Storage Area (PFSA) (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FTA-2 Former Fire Training Area (9) | Feb-90 | May-92 | Nov-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| FTA-3 Former Fire Training Area (9) | Mar-89 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| CY-4 Current Coal Storage Yard (9) | Mar-89 | Sep-92 | Aug-93 | Jul-96 | Feb-97 | Feb-98 | F Sept 98 | 06-Dec-99 | |||
| Priority 2 and 3 Sites and DDOU | |||||||||||
| CS-5 Former Refueler Maintenance Shop (14) | Nov-93 | 06-Dec-99 | |||||||||
| CS-11 Former Pest Control Area (14) | Nov-93 | 06-Dec-99 | |||||||||
| CS-15 Former Engine Run-up Area (14) | Nov-93 | 06-Dec-99 | |||||||||
| FS-4 Current Product Tank 100/101 (14) | Nov-93 | 06-Dec-99 | |||||||||
| FS-18 Fuel Transfer Point (14) | Nov-93 | 06-Dec-99 | |||||||||
| CS-4 CG Hanger 128 Area (14) | Nov-93 | 06-Dec-99 | |||||||||
| FS-1 CG Hanger 128 Fuel Spill (14) | Nov-93 | 06-Dec-99 | |||||||||
| FS-7 Current Product Tank 115 (14) | Jul-95 | 06-Dec-99 | |||||||||
| CS-16/CS-17 DDOU (14) | Mar-96 | 06-Dec-99 | |||||||||
| CS-3 CG BX Service Station USCG | Nov-93 | Apr-93 | Aug-94 | Sep-96 | Dec-97 | May-98 | F Sept 98 | 06-Dec-99 | |||
| CS-16/CS-17 STP Sludge Disposal | Dec-90 | May-93 | Mar-95 | Sep-96 | Dec-97 | Nov-98 | F May 99 | 06-Dec-99 | |||
| CS-10 UTES / FS-24 BOMARC Site Source | Mar-89 | May-92 | Nov-93 | Oct-96 | Dec-97 | Dec-98 | F Aug 99 | 06-Dec-99 | |||
| FS-9 Current Product Tank 108 | Nov-93 | Mar-93 | May-98 | 29-Jun-98 | 12-Aug-98 | Dec-98 | F July 99 | 06-Dec-99 | |||
| FS-17 Former WWII Motor Pool/Fuel Transfer Point | Nov-93 | Feb-93 | May-98 | 12-Aug-98 | 08-Feb-99 | ||||||
| FS-19 Former MOGAS Fuel Storage & Transfer Point | Nov-93 | Jan-93 | May-98 | 12-Aug-98 | 08-Feb-99 | ||||||
| FS-1 AVGAS Test Dump Site | Feb-90 | Jun-90 | Jul-98 | Oct-98 | Mar-99 | 16-Aug-99 | |||||
| LF-4 John's Pond Dump-Off Base (10) | Jun-99 | ||||||||||
| CS-13 Former Contractor Yard (11) | |||||||||||
| Date Activity Completed | |||||||||||
| NOTES: 1. These 11 sites were identified in the Phase I Records Search. After a site visit was conducted with EPA/DEP, it was agreed that no further activities were warranted and a no further action Decision Document would be prepared for the sites. 2. A draft RI for FS-2 was issued in Aug 91and there were subsequent follow on supplemental investigations. AFCEE will be submitting a completion schedule to EPA in September 1999. 3. Cleanup at the site was performed under a non-time critical removal action in FY95-97. 4. Once the Supplemental Site Investigation is completed, AFCEE will submit a draft DD in six months or a draft RI/FS Work Plan in eight months. 5. The Site Investigation is complete. A Supplemental Site Investigation is being accomplished. The draft SSI Tech Memo is due 5 Feb 2000. 6. The LF-1 Groundwater Operable Unit Remedial Investigation and the results from downgradient field work will be evaluated to determine the deposition of the LF-1 Northwest Operable Unit. Upon finalization of the RI, AFCEE will either submit a "No Further Action Proposed Plan" within six months or a "Feasibility Study" within eight months. 7. Cleanup at the site was performed under a time critical removal action in FY 96-97. 8. Cleanup at the site was performed under a non-time critical removal action in FY95-97. 9. This grouping of sites is referred to as the "6 Areas of Concern (6 AOC)". All the sites are proceeding on the same schedule. 10. Depending upon the recommendations of the LF-4 Site Investigation Report, AFCEE will either submit a draft Decision Document by 31 December 1999 or a draft Remedial Investigation Work Plan by 31 January 2000. 11. The site was initially identified through the Phase I Records Search as an Area of Concern. Currently, AFCEE is investigating whether the site is appropriately addressed under the FFA because of questions over property ownership. 12. These documents are not enforceable milestones but are shown for information purposes. 13. A Preliminary Assessment/ Site Investigation is underway to determine if contamination exists which warrants further investigation. 14. Final EE/CA completed Oct 98. Draft AM submitted Feb 99. |
|||||||||||
| Site | Draft Site Investigation (4) | Draft RI/FS Work Plan | Draft Remedial Investigation | Draft Feasibility Study | Draft Proposed Plan | Draft Record of Decision | Final Record of Decision (6) | FINAL Remedial Design | Draft Recirc Exec Plan | Complete 1st 10 Wells |
| CS-4 West Truck Road Motor Pool | Feb-90 | Feb-92 | Feb-92 | Apr-92 | F May 92 | Jul-92 | ||||
| FS-12 Underground Fuel Line Range | Oct-90 | Mar-92 | Dec-93 | Jun-94 | Nov-94 | May-95 | F Sept 95 | |||
| SD-5 North Containment System | Feb-90 | Sep-92 | Nov-93 | Jun-94 | Nov-94 | May-95 | F Sept 95 | |||
| SD-5 South Remedial Action - Recirc (1) | Feb-90 | Sep-92 | Nov-93 | Jun-94 | Nov-94 | May-95 | F Sept 95 | 18-Oct-96 | ||
| SD-5 South Remedial Action - ETR (1) (7) | ||||||||||
| LF-1 Groundwater Operable Unit (1) | Feb-90 | Sep-92 | May-94 | Jun-94 | Nov-94 | May-95 | F Sept 95 | 21-Oct-96 | ||
| East Briarwood/Western Aquafarm (1) (2) | Feb-90 | Sep-92 | Nov-93 | Jun-94 | Nov-94 | May-95 | F Sept 95 | |||
| Ashumet Valley Groundwater Operable Unit (3) | Jul-88 | May-93 | Apr-95 | Jun-94 | Nov-94 | May-95 | F Sept 95 | 17-Oct-96 | 18-Dec-96 | |
| Ashumet Pond Draft Phosphorus Management Plan | ||||||||||
| AV Axial Fence (With Falmouth Conservation Area) | ||||||||||
| CS-10 Groundwater Operable Unit (1) | Feb-90 | Sep-92 | Nov-93 | Jun-94 | Nov-94 | May-95 | F Sept 95 | 23-Aug-96 | 31-Oct-96 | |
| CS-10 Sandwich Road Fence | ||||||||||
| CS-10 Southern/ Southwest Fence | ||||||||||
| CS-10 In-Plume | ||||||||||
| CS-10 GWOU/ Leading Edge/ Final ROD | 10-Feb-00 | 24-Oct-00 | 11-Jun-01 | 02-Nov-01 | 03-Mar-02 | |||||
| FS-1 AVGAS Test Dump Site | Feb-90 | Jun-90 | 20-Jul-98 | 14-Oct-98 | 16-Mar-99 | 16-Aug-99 | ||||
| SWOU AOC EDB Release | Mar-98 | Oct-98 | 20-Jan-99 | 16-Mar-99 | 27-Sep-99 | |||||
| CS-4 Plume (TCE & PCE) | Mar-98 | Oct-98 | 20-Jan-99 | 16-Mar-99 | 27-Sep-99 | |||||
| CS-20 Plume (TCE & PCE) | Mar-98 | Oct-98 | 20-Jan-99 | 16-Mar-99 | 27-Sep-99 | |||||
| CS-21 Plume (TCE) | Mar-98 | Oct-98 | 20-Jan-99 | 16-Mar-99 | 27-Sep-99 | |||||
| FS-13 Underground Fuel Line Cantonment | Mar-98 | Oct-98 | 20-Jan-99 | 16-Mar-99 | 27-Sep-99 | |||||
| SWOU (FS-28) EDB Plume | 11-Jul-99 | 29-Sep-99 | 25-Mar-00 | |||||||
| SWOU (FS-29) EDB Plume | 11-Jul-99 | 29-Sep-99 | 25-Mar-00 |