August 1997 Federal Facility Agreement Schedule Changes A fact sheet providing an update on the Federal Facility Agreement. The purpose of this fact sheet is to describe the updates that have been made to the schedules which are a part of the Federal Facility Agreement (FFA). The FFA is an agreement between the Air Force Center for Environmental Excellence (AFCEE), the National Guard Bureau, the U.S. Coast Guard, and the U.S. Environmental Protection Agency (EPA) that guides the cleanup of the Massachusetts Military Reservation (MMR). The FFA contains the operative schedules for all sites on the base that are being investigated under the Installation Restoration Program, the base cleanup program for past environmental contamination. The first schedule, contained in Appendix III, Timetable 2 of the FFA, established enforceable dates for numerable ongoing source control actions at the MMR. Specifically, this schedule set deadlines for decisions for areas requiring soil and sediment cleanup. This schedule was last updated in August 1995. The second schedule contains the enforceable dates pertaining to plume response actions, the cleanup of contaminated groundwater, at and originating from the MMR. This schedule was added to the FFA as Appendix III, Timetable 3 on May 30. 1997. Under the FFA, extensions of enforceable deadlines may be granted by EPA under certain circumstances which are determined to constitute good cause. Some of the circumstances which led to extensions or other changes in the schedule include:
The following tables indicate where changes to previous dates have been made. The first table indicates the changes made to source control deadlines (Timetable 2); the second summarizes the revisions to the plume response schedule (Timetable 3). Each table references the source area or plume affected, the document to which the deadline applies, the former date, the revised date, and the justification for making the change. EPA has agreed to the changes. EPA and AFCEE regularly consult with the state on major schedule changes. None of the extensions granted to date have resulted in any changes to end dates for plume response activities. The timetable for ultimate plume decisions remains on schedule. Therefore, EPA and AFCEE believe that the revised schedules represent aggressive yet realistic timetables for the implementation of the MMR cleanup. Several acronyms used in the tables are defined at the end of this fact sheet. For more information, please contact: Vanessa Musgrave |
SOURCE CONTROL ACTIONS |
||||
AOC |
Document |
Old Date |
New Date |
Reason for Change |
| CS-1 CS-2 CS-3 FS-23 CS-2 (CG) CS-9 CS-14 |
DD DD DD DD DD DD DD |
none none none none none none none |
4/97 4/97 5/97 5/97 6/97 5/97 5/97 |
Completed the DSRP for source area closure prior to submitting Decision Document |
| CS-10 Source | FS PP ROD |
10/95 5/96 12/96 |
10/96 12/97 5/98 |
The shutdown of the Federal government delayed the receipt of funding to support contract activity and the EPA required additional time to complete review of the feasibility study resulting in an extension of time for future activities |
| SD-4 | PP ROD |
6/96 3/97 |
2/97 9/97 |
EPA required additional time to complete review of the feasibility study resulting in an extension of time for future activities |
| FS-19 | FS PP ROD |
5/96 12/96 9/97 |
9/96 9/97 2/98 |
Revisions to the Risk Assessment Handbook necessitated a rewrite of the RI Report. A decision was made to do a multi-site FS to |
| FS-17 | FS PP ROD |
3/96 10/96 7/97 |
9/96 9/97 2/98 |
expedite the selection of a remedial alternative by combining sites with similar characteristics |
| FS-9 | FS PP ROD |
4/96 11/96 8/97 |
9/96 9/97 2/98 |
|
| CS-3 (CG) | FS PP ROD |
2/96 8/96 3/97 |
9/96 9/97 2/98 |
|
| LF-2/FTA-2 | FS PP ROD |
12/95 6/96 1/97 |
7/96 2/97 9/97 |
|
| SD-5/FS-5 | FS PP ROD |
12/95 6/96 1/97 |
7/96 2/97 9/97 |
|
| PFSA/ FS-10/FS-11 |
FS PP ROD |
12/95 6/96 1/97 |
7/96 2/97 9/97 |
|
| CS-16/17 | FS PP ROD |
12/95 6/96 1/97 |
9/96 9/97 2/98 |
|
| SD-3/ FTA-3/CY-4 |
FS PP ROD |
12/95 6/96 1/97 |
7/96 2/97 9/97 |
|
| SD-2/ FS-6/FS-8 |
FS PP ROD |
12/95 6/96 1/97 |
7/96 2/97 9/97 |
|
| FS-1 | RI PP ROD |
TBD | 11/97 2/98 9/98 |
Additional field work summer of 1997 with revised RI report to be prepared |
| FS-2 | RI | TBD | TBD | Site will be included in SWOU effort |
GROUNDWATER PLUME RESPONSE ACTIONS |
||||
AOC |
Document |
Old Date |
New Date |
Reason for Change |
| FS-12 Plume | Phase II System Start-up | TBD | 5/15/98 | Project scoping needed to be completed prior to setting schedule |
| CS-10 Plume | Completion of 2 pilot ETR extraction wells | 6/3/97 | deleted | Approach for the Pilot ETR was modified to a Conceptual Design, the Data Gap Tech Memo replaced the pilot ETR Test Data Report without a schedule change |
| Ashumet Valley Plume | Draft Full Scale Execution Plan | 10/9/97 | 10/28/97 | Approach for the Pilot ETR was modified to a Conceptual Design, the Data Gap Tech Memo replaced the pilot extraction wells and ETR Test Data Report |
| LF-1 Plume | Recirculating Well Technical Assessment Report | 10/15/97 | 9/17/97 | Approach to the Recirculating well pilot test was changed to Technology Input. Intermediate steps for field construction and start-up were eliminated and replaced with data extrapolation shortening the schedule |
| LF-1 Plume | Completion of 2 Pilot ETR extraction wells | 7/23/97 | deleted | Approach for the Pilot ETR was modified to a Conceptual Design, the Data Gap Tech Memo replaced the pilot extraction wells and ETR Test Data Report without a schedule change |
| SD-5 South Plume | Recirculating Well Technical Assessment Report | 1/31/98 | 10/22/97 | Approach to the Recirculating well pilot test was changed to Technology Input. Intermediate steps for field construction and start-up were eliminated and replaced with data extrapolation shortening the schedule |
| SD-5 South Plume | Completion of 2 Pilot ETR extraction wells | 8/26/97 | deleted | Approach for the Pilot ETR was modified to a Conceptual Design, the Data Gap Tech Memo replaced the pilot extraction wells and ETR Test Data Report without a schedule change |
| SD-5 South Plume | Draft Full Scale Execution Plan | 3/24/98 | 2/2/98 | Approach change to Conceptual Design shortened the schedule by eliminating the field pilot test |
| Western Aquafarm Eastern Briarwood Monitoring | Annual Evaluation Report | TBD | 9/30/97 | Project scoping needed to be completed prior to setting schedule |
Dates were based on a comparison between:
Acronyms
|